Rocky Mountain Power
        For Your Home For Your Business

 

Electric Service Requirements

Do you need to start new electric service? We can help you get plugged in. Before you start the process, check out the links below to get information on our electric service requirements. Each of the sections of the manual are in PDF format and require a reader for viewing. To download a free reader, visit Adobe's Web site. You can also get a list of approved meter service equipment.

Contents - Title and table of contents
Section 1 - General requirements
Section 2 - Permits and applications
Section 3 - Service and meter installation 
Section 4 - Temporary construction service
Section 5 - Clearances
Section 6 - Underground requirements  
                (Fiberglass Conduit may be used in accordance with PacifiCorp Material
                Specification ZG 033, Fiberglass Conduit)         
Section 7 - Single-family service
Section 8 - Multiple-family service
Section 9 - Manufactured and mobile home service
Section 10 - Commercial, industrial and agricultural services
Index

Six State ESR (Entire book)

Questions and comments about the ESR book can be submitted via e-mail to:
esrfeedback@pacificorp.com

 

Net Metering Requirements:

Idaho
Authorized Generation Types and kW Limits
Interconnection Agreement for Net Metering Service up to 25 kW (for schedules 1,23, 23A, and 36)
    -Includes Appendix A,  Application for Net Metering Interconnection
Interconnection Agreement for Net Metering Service up to 100 kW (for schedules not listed above) 
    -Includes Appendix A, Application for Net Metering Interconnection

Utah
Authorized Generation Types and kW Limits
Interconnection Agreement for Net Metering Service   
    -Includes Appendix A, Application for Net Metering Interconnection

Wyoming
Authorized Generation Types and kW Limits
Interconnection Agreement for Net Metering Service
    -Includes Appendix A, Application for Net Metering Interconnection