Ben Lomond to Terminal project

Project overview

As part of the Terminal to Populus segment, the Ben Lomond to Terminal project will add 345 kV transmission lines along 46 miles from the Ben Lomond substation in Box Elder County to the Terminal substation located near the Salt Lake City airport. More details are included in this fact sheet  and map . You can also read about the project in this newsletter  for our customers.

More documents relating to the project will be available soon. Please check back.

Project timing

  • Informational meetings -- August - November 2007
  • Permitting and obtaining rights of way -- December 2007 - July 2008
  • Construction -- June 2008 - March 2010
  • Bring line in service -- March 2010




(Updated May 19, 2008)